City of Pirot

SITUATION BEFORE THE CONTRACT AND CLIENT REQUIREMENTS

The City of Pirot announced a public tender in order to lower heating
costs in four schools and improve efficiency.

All four schools had obsolete and unreliable crude oil boilers, a solution
that wasn’t environmentally friendly.

GGE SOLUTION

In order to improve efficiency and lower the environmental impact, GGE
installed two biomass boilers in each school:
Dairy high school 360 kW + 120 kW
Elementary school 8. septembar 450 kW – 120 kW
Elementary school Duško Radović 550 kW + 120 kW
Elementary School Sveti Sava 240 kW + 120 kW.
Biomass is an efficient, locally sourced and environmentally friendly fuel
Contract duration is 7 years

RESULTS

0 %
Savings on energy costs
0 t
CO2 emissions cut each year

STATUS – ONGOING

YEAR

2017